ENG-21 · Engineering consultancy

Compressed-air loss cost assessment

Estimate whether out-of-hours compressor demand warrants a site survey or repair budget.

What to share
Compressor power or energy readings, operating schedules and details of essential air users.
How we help
Compare actual out-of-hours electricity use with the demand your site can explain.
What you receive
A cost-range workbook, a breakdown of assumptions and a targeted brief for site verification.

When this service helps

Compressor electricity can be hidden in a site-wide bill. A machine that cycles while production is stopped may be serving essential equipment, compensating for leaks or responding to its control settings. A remote assessment gives management a range to investigate before approving survey spend. It also helps the site team choose what to measure if the existing records cannot distinguish the causes.

How we help

We compare the periods in your records, identify shutdowns when conditions were similar and check whether essential users were still connected. Where information is incomplete, we show how that affects the estimate and prepare questions for the responsible site engineer. Motor nameplate capacity alone cannot establish actual energy use.

What you receive

Your budget owner gets the working figures and a clear explanation of what could justify a physical survey. The site’s appointed team arranges inspections, safe access, testing and repairs. The review can also identify when another short period of metering would be the more proportionate first expense.

An example for your business case

An illustrative compressor averages 16 kW during 1,500 shutdown hours a year. If the site confirms that 6 kW is required, the remaining 10 kW represents 15,000 kWh to investigate. At an assumed £0.20 per kWh, that gives £3,000 of annual electricity exposure. The achievable reduction depends on what the survey finds and how the compressor controls respond.

Start the discussion

Tell us when the compressor normally runs, when production stops and why the cost has attracted attention. If you know whether actual power or energy readings exist, mention that in your email. We can discuss a useful starting period before requesting operational records.

Email [email protected] with the decision date and quote ENG-21. We can agree the scope and a suitable way to share any sensitive records during the first discussion.

How it works

  1. Check the schedule
  2. Compare actual demand
  3. Allow for essential loads
  4. Decide on a survey
Illustrative business case

Illustrative annual out-of-hours exposure

average demand
16 kW
required demand
6 kW
cost to investigate
£3,000

Illustrative business case · ENG-21

Is an out-of-hours compressed-air survey worth funding?

See how the example was calculated, which assumptions change the result and what to check with your own figures.

PDF · 2 pages · 93 KB

Read the full business case

ENG-21 · Compressed-air loss cost assessment · OXETC business-case whitepaper · Version 1.0, November 2026

The management decision

Use existing records to estimate how much electricity the compressor uses outside production. Confirm necessary demand with site personnel before treating the remaining amount as an opportunity worth a field survey.

Compressor electricity can be hidden in a site-wide bill. A machine that cycles while production is stopped may be serving essential equipment, compensating for leaks or responding to its control settings. A remote assessment gives management a range to investigate before approving survey spend. It also helps the site team choose what to measure if the existing records cannot distinguish the causes.

Worked example

An illustrative compressor averages 16 kW during 1,500 shutdown hours a year. If the site confirms that 6 kW is required, the remaining 10 kW represents 15,000 kWh to investigate. At an assumed £0.20 per kWh, that gives £3,000 of annual electricity exposure. The achievable reduction depends on what the survey finds and how the compressor controls respond.

Example figureWhat it represents
16 kWAverage demand
6 kWRequired demand
£3,000Cost to investigate

What changes the answer

If essential use is actually 10 kW, the unexplained portion falls to 6 kW. Across the same hours and tariff the exposure falls to £1,800. A survey quote can be considered against both cases, allowing separately for repair costs.

What to commission

Assess one compressed-air system during an agreed production and shutdown period using existing records.

We compare the periods in your records, identify shutdowns when conditions were similar and check whether essential users were still connected. Where information is incomplete, we show how that affects the estimate and prepare questions for the responsible site engineer. Motor nameplate capacity alone cannot establish actual energy use.

How to judge the result

The site lead can reproduce the cost range and distinguish verified necessary demand from loss that still needs field confirmation.

Compare the cost of surveying and repairing confirmed losses with the value of the avoidable electricity. Verify performance after repair over a comparable operating period.

Decision worksheet

Project detailStarting point for your team
Decision ownerEngineering manager or facilities budget owner. Name the person who will approve the next step.
Records to gatherCompressor power or energy readings, operating schedules and details of essential air users.
Agreed outputA cost-range workbook, a breakdown of assumptions and a targeted brief for site verification.
Decision dateRecord the deadline, any unresolved assumption and who will confirm it.

Discuss this case

Tell us when the compressor normally runs, when production stops and why the cost has attracted attention. If you know whether actual power or energy readings exist, mention that in your email. We can discuss a useful starting period before requesting operational records.

Email [email protected] and mention ENG-21. All figures in the worked example are illustrative.